Title:
|
Approve Contract Change Order and Increase Contract Amount for Recycled Water System - Phase 1A, C.O. No. 8087
Recommended Action:
It is recommended that the Board of Directors of the Hesperia Water District approve the proposed Contract Change Order to the contract with Christensen Brothers General Engineering, Inc. for Recycled Water System - Phase 1A (C.O. No. 8087) in the amount of $730,107; approve an additional 10% contingency in the amount of $72,893; and authorize a revised total construction budget of $7,111,056 in order to increase the contract scope of work.
|