Title:
|
Approve Contract Change Orders and Increase Contract Amount for Recycled Water System - Phase 1B, C.O. No. 8087
Recommended Action:
It is recommended that the Board of Directors of the Hesperia Water District approve the proposed Contract Change Orders to the contract with R.I.C. Construction Company, Inc. for Recycled Water System - Phase 1B (C.O. No. 8087) in the amount of $235,828.97; approve an additional 10% contingency in the amount of $23,580.00; and authorize a revised total construction budget of $5,404,540.34.
|